(239)774-0026

Verona Walk Landscape Schedule Weeks of 11/10 and 11/17

November 10, 2025

Here’s a Preview of Your Upcoming Landscape Services

Pruning:
Streets pruned in the last two weeks,  Erice, Ferrara, Adriana, Bellini, Carducci, Dontello, Garibaldi, and Ionio.

Week of 11/10 Pruning Schedule:

  • Team (1) Portofino, and Rozzini
  • Team (2) Valentina, and Wilfredo
  • Team (3) Zurigo, and Genova
  • Team (4) Common Areas (Veronawalk Circle)

Week of 11/17 Pruning Schedule:

  • Team (1) Rozzini, and Sicilia
  • Team (2) Wilfredo
  • Team (3) Genova, and Karina
  • Team (4) Common Areas (Veronawalk Circle)

Week of 11/24 Pruning Schedule:

  • Team (1) Sicillia, and Tommasi
  • Team (2) Xenia 
  • Team (3) Karina
  • Team (4) Common Areas (Veronawalk Circle)

Week of 12/01 Pruning Schedule:

  • Team (1) Tommasi
  • Team (2) Yasmina, Veronawalk Blvd
  • Team (3) Benelli
  • Team (4) Common Areas (Veronawalk Circle)

Week of 12/08 Pruning Schedule:

  • Team (1) Sicilia
  • Team (2) Sorrento Ln, and Josefa
  • Team (3) Benelli, and Julia
  • Team (4) Common Areas (Veronawalk Circle)

Plant Fertilizer and Weed/Pest Control: 

  • Turf Fertilizer Starting (10/13) (16-0-8)
  • Turf Fertilizer Completed (9/4) (0-0-0) Sulfur
  • Turf Fertilizer Completed (5/21) (16-0-8)
  • Turf Fertilizer Completed (2/14) (16-0-8)
  • Turf Weed/Pest Control Starting (10/13)
  • Turf Weed/Pest Control Completed (7/15) (Spot Spray)(Chinch Bug)
  • Turf Weed/Pest Control Completed(5/21)(Spot Spray)
  • Turf Weed/Pest Control Completed (3/19)

Fertilizer and Weed Control Schedule:

Maintenance Weekly Mowing Map:

  • Mow Schedule will change on (10/27)
  • Week of 11/10 (Hard Edging)
  • Week of 11/17 (Hard Edging)    

Tree/Palm Pruning and Removals

  • Oak Tree Pruning Completed (4/4) (Johnson’s Tree Service)
  • Palm Pruning Completed (4/4) (Johnson’s Tree Service)
  • Queen Palm Removals Completed (2/14) (Johnson’s Tree Service)
  • Queen Palm Removals Completed (6/24) (Greenscapes)
  • Dead/Declining Magnolia/Holly Tree Removals Completed (8/1) (Greenscapes)
  • Palm Removals Completed (8/21)(Greenscapes)
  • Coconut Palm Pruning Completed (11/07)(Greenscapes)

Upcoming landscaping installations:

  • January/February Sod Zendesk Tickets Completed (3/19)
  • March/April/May Sod Tickets completed (6/26)
  • June/July Sod Tickets Completed (8/28)
  • August/September Sod Tickets Completed (10/16)
  • October Sod Ticket (November)
  • Zendesk Tickets are being reviewed for November (Landscape Committee)
  • Flower Rotation Competed (3/27) 
  • Flower Rotation Completed (6/26)
  • Flower Rotation Completed (10/29)
  • Town Center Proposals Started (11/3)

Please See Additional Details About Your Services Below