Here’s a Preview of Your Upcoming Landscape Services
Started May 12th Tuesday Town Center with Greenscapes will change to 10am – 11am and resume 2-hour sessions 10/6
Pruning Cycle Starting (6/22)
Week of 8/31 Pruning Schedule: Growth Regulator will be sprayed on Friday (9/04)
- Team (1) Salerno
- Team (2)Sicilia, and Tomassi
- Team (3) Zurigo, and Karina
Week of 9/07 Pruning Schedule: Growth Regulator will be sprayed on Friday (9/11)
- Team (1) Toscana, and Leopardi
- Team (2) Tomassi
- Team (3) Karina
Week of 9/14 Pruning Schedule: Growth Regulator will be sprayed on Friday (9/18)
- Team (1) Leopardi, and Marconi
- Team (2) Umberto
- Team (3) Benelli
Week of 9/21 Pruning Schedule: #fffd01
- Team (1) Marconi
- Team (2) Umberto, and Valentina
- Team (3) Julia

Plant Fertilizer and Weed/Pest Control:
- Turf Fertilizer/Pre-Emergent Completed (4/3)(25-0-5)
- Turf Fertilizer/Turf Weed Control Started (7/27) (0-0-0) (Sulphur)
- Palm Fertilizer Completed (4/3)(8-2-12)
- Treating Deficient Plants Completed (4/3)
- Plant Growth Regulator 1st Application Completed (4/10)
- Plant Growth Regulator 2nd Application Started (6/22)
Maintenance Weekly Seasonal Mowing Map:
- Week of 8/31 (Soft Edging)
- Week of 9/07 (Hard Edging)
- Sabal Palm Rd Completed (5/21)
- Sabal Palm Rd Completed (6/18)
- Sabal Palm Rd Completed (7/16)
- Sabal palm Rd Completed (8/13)

Tree/Palm Pruning and Removals
- Palm Pruning Completed (8/19)
- Palm Removals Completed (2/2)
- Palm Removals Completed (3/31)
Upcoming landscaping installations:
- June, July, and August Sod Tickets Proposing (September)
- Sod Proposal (Drought) Completed (7/29)
- Veronawalk Blvd Bridge Completed (8/4)
- Flower Rotation Completed (5/7)
- July Zendesk Proposals (August)
- Green Buttonwood Trees Completed (2/25)
- Veronawalk Circle Islands Completed (2/19)
- Sorrento Bridges Completed (2/19)
Landscape Article: Florida Lawn Weed Control