(239)774-0026

Verona Walk Landscape Schedule Weeks of 8/18 and 8/25

August 18, 2025

Here’s a Preview of Your Upcoming Landscape Services

Pruning:
Streets pruned in the last two weeks, Wilfredo, Valentina, Umberto, Orvieto, Portofino, and Tommasi have 12 houses to complete.

Week of 8/18 Pruning Schedule:

  • Team (1) Tommasi, Rozzini and Xenia
  • Team (2) Tommasi, Rozzini and Xenia
  • Team (3) Karina

Week of 8/25 Pruning Schedule:

  • Team (1) Xenia, Yasmina, and Ravello
  • Team (2) Xenia, Yasmina, and Sorrento 
  • Team (3) Benelli

Plant Fertilizer and Weed/Pest Control: 

  • Turf Fertilizer Starting (8/18)
  • Turf Fertilizer Completed (2/14) (16-0-8)
  • Turf Fertilizer Completed (5/21) (16-0-8)
  • Turf Weed/Pest Control Completed (3/19)
  • Turf Weed/Pest Control Completed(5/21)(Spot Spray)
  • Turf Weed/Pest Control Completed (7/15) (Spot Spray)(Chinch Bug)

Fertilize Schedule

  • Week of 8/18 Red, and Blue
  • Week of 8/25 Blue, and Green

Maintenance Weekly Mowing Map:

  • Week of 8/18 (Soft Edging)
  • Week of 8/25 (Hard Edging)
  • Sabal Palm Rd Completed (6/19)
  • Sabal Palm Rd Completed (7/17)
  • Sabal Palm Rd Completed (8/14)

Tree/Palm Pruning and Removals

  • Oak Tree Pruning Completed (4/4) (Johnson’s Tree Service)
  • Palm Pruning Completed (4/4) (Johnson’s Tree Service)
  • Queen Palm Removals Completed (2/14) (Johnson’s Tree Service)
  • Queen Palm Removals Completed (6/24) (Greenscapes)
  • Dead/Declining Magnolia/Holly Tree Removals Completed (8/1) (Greenscapes)
  • Palm Removals Starting (8/21)

Upcoming landscaping installations:

  • January/February Sod Zendesk Tickets Completed (3/19)
  • March/April/May Sod Tickets completed (6/26)
  • June/July Sod Tickets Starting (8/25)
  • Zendesk and Kwik Tickets are being reviewed for August (Landscape Committee)
  • Flower Rotation Competed (3/27) 
  • Flower Rotation Completed (6/26)

Please See Additional Details About Your Services Below